And another update from Jeff:
Hello ShareRoller Indiegogo backer:
Good news: At long last we've received the first batch of battery packs and chargers. Our supplier managed to deliver a partial shipment prior to the Chinese New Year shutdown, and we now have 100 battery packs and chargers in stock and ready to ship and they look great. We expect to receive the next batch in another month. Here are some photos of the first batch in our space - after over two years of development and enormous amounts of engineering time and cost, we're incredibly excited to finally have them here!
Sorting out our 3D-printed plastics has taken us a lot longer than planned however. While our in-house Stratasys Fortus FDM 3D printer has been great for development and prototyping (it's ultra-fast for small builds and has phenomenal accuracy), the surface finish and part strength isn't quite good enough for production (we had to sand and paint all the parts used in our photoshoot). And the next step up machines approach $1 million in cost, so we have no choice but to outsource. As a result, we've tested multiple suppliers for both traditional SLS (Selective Laser Sintering) and the newest HP MJF (Multi-Jet Fusion) parts over the past several months. Btw, if you're not familiar with the latest HP MJF printers, do take a look as it's absolutely incredible tech:
We've been through multiple rounds of production samples and revisions with multiple suppliers, and had to push hard to get both the part accuracy and surface finish (and price!) that we required. Let's just say our vendors probably have us in the PITA customer category at this point. However, we've finally arrived at a fantastic solution with a US-based MJF part manufacturer that happens to be the biggest in the world. The parts are incredibly strong and have an amazing finish called Carbonite that has a quasi-titanium color. Here’s a pic of an unassembled OneMotor with Carbonite MJF samples showing how it looks with the black battery packs and blue motor belt - it really makes for a stunning combo!
We validated final MJF production samples early this week and the supplier is now starting off with volume runs – they’re scheduled to get us our first production shipment next week, with subsequent batches following every week or two.
So we will begin final assembly next week once we receive the production MJF parts and then the only remaining ‘formality’ is our FCC certification, which is now scheduled for Wed 2/20. Thus, everything’s finally coming into place and we hope to start deliveries of the first few units the week of 2/25 or 3/4. As we mentioned before, production will ramp slowly so it will take 2-3 months before we can ship all units, however we're going to do all we can to ensure everyone receives their OneMotor by Spring.
Oh, and one other bit of news – we’ve recently developed a new mount for high-end road bikes, but it will fit any bike with external cup threaded bottom brackets (like Shimano Hollowtech) including mountain bikes. Here’s how it looks on a carbon fiber road bike we have in-house – really glad we were able to fit such a space-constrained platform! So if you happen to have a compatible road or mountain bike, perhaps something to think about…
Once your order is within a week of shipment, we will send out the Invoice for any additional funds from the Google Form accessories update. In the meantime, please feel free to reach out with any further questions.
Thank you again for your patience and support.